Concrete mixing plant concrete mixing plant mainly by the mixing console, material weighing system, material handling systems, material storage systems and control systems and other five major system components and other ancillary facilities.
2013年8月28日星期三
mixing station empty commissioning
1) Start stirring motor, two stirring shaft steering and signs should indicate the same direction. 2) vigorously fight foot pressure compressor, start discharging mechanism, discharge door opening and closing should be accurate place. 3) Start the pump to draw water, the water supply system should operate normally. 4) Wheel Loader lifting winch motor, hopper raised to unloading position, should automatically stop, Doumen open automatically. Hopper in operation, such as motor power, brake motor brake can live hopper, hopper then fell more than if 150mm, specifying the braking torque is too small, you should adjust the braking force; hopper drops, concrete mixing machine level of turnout Card live, down to the pit bottom, the rope a little loose, winch mechanism should automatically stop. 5) In the above commissioning process, if found to be not normal circumstances, you should downtime, complete troubleshooting only after the concrete mixing operation.
订阅:
博文评论 (Atom)
没有评论:
发表评论